Back to Production
BC-J-26003
Umbria dining table · Noosa
Production piece
Details
- Status
- Casting
- Order
- BC-O-26003
- Colour / finish
- Whitehaven
- Work area
- Casting bench
- Due date
- 19 Nov 2026
- Scheduled date
- 19 Nov 2026
- Primary material
- FRC base mix
- Mix requirement
- 25 kg
- Material status
- Issued
- Sample
- Approved
Production stages
Six workshop stages. Casting issues the recorded primary mix; insufficient stock blocks the move.
Mould preparation
Reinforcement
Casting
Curing
Finishing
Ready to dispatch
Notes
Approved drawings on file.
Order context
Umbria dining table · Noosa
BC-O-26003